Overview
This invitation for bids concerns the construction and completion of underground sewerage networks and in-line pumping stations in Puducherry as part of the Puducherry Integrated Urban Livability Improvement Project.
Tasks Summary
- Providing and Laying Underground Sewerage Networks in Zones 13 - Park and 14- 2
- Constructing In- line Pumping Stations 13- Park - 6, 13 -Park -1 and 14-2- 1
- Laying of DWC Sewer Pipes 49 km
- Laying of HDPE Sewer Pipes using Trenchless methods 6 km
- Providing House Service Connections 4800 Nos
- Installing Inlie sewage boosters 3 Nos
Experience Requirements
- Average Annual Construction Turn Over 45.7 Crores INR
- Financial resources 7.6 Crores INR
- Contracts of Similar Size: One Contract of size 73.1 Crores INR
- Laying Sewers 25 km
- Laying sewers by trenchless technology 1.5 km
- Sewer house service connections 1000 Nos
- Construction of sewer pump or lift stations or inline boosters 1 Nos
Qualification Requirements